Overview

EDS/Exxon Mobil commissioned Liberty Industrial to demolish the entire Port Stanvac Oil Refinery, including the process plant and piping, storage tanks, chimney stack, flare stacks and other associated above ground facilities such as office buildings, electrical substations, warehouses, maintenance workshops and control rooms. The Project also included removal of all pipework and other oil handling facilities located on the wharf structure.

Challenges

  • Ensuring minimal environmental impact on the surrounding coastline of the Gulf St Vincent.
  • Never before had an entire refinery demolition project been attempted and it was left to Liberty Industrial to pave the way for others to follow.

Robust Solutions/Exceptional Outcomes

Robust solutions

  • Meticulous planning and extensive consultation to assess and mitigate asbestos exposure to environment and crew.
  • Development of a detailed hydrocarbon containment and asbestos removal logistics program.
  • Liberty Industrial mobilised a highly specialised crew alongside state-of- the-art plant and equipment.
  • Provided an arsenal of excavators ranging from 36 to 120t, alongside a selection of demolition attachments

 

Exceptional outcomes

The project was masterfully executed as planned to client’s complete satisfaction, on budget, on schedule and without injury or incident.

Value Add

01

Demolition Simulation and Modelling

With exclusive license to demonstrate using Extreme Loading® for Structures (ELS) software developed by Applied Sciences International (ASI).

02

Deconstruction

Use of best approach demolition and dismantling such as explosive using world class fleet, safety and engineering methodologies in explosives and rigging.

03

Asset and Resource Recovery

Comprehensive waste and recycling management to contribute to the circular economy to extend the lifecycle of materials.

04

Site Remediation

Site rehabilitation via methods such as bioremediation, containment, decontamination, dewatering, stabilisation, treatment and tracking to disposal of contaminants.

values-bg

World’s Most Powerful Shear Unveiled in Australia

Gove Refinery Closure Project

News

WGEA Reporting

People and Culture

integrated capability responsible decommissioning

decommissioning closure and asset liability consulting

consulting risk management engineered solutions 3d simulation

and simulation liberty modelling dismantling and asset

dismantling and asset recovery synchronised safety

deconstruction resource recovery and recycling expert delivery

high expert industrial delivery reach consulting

expert delivery high reach explosive induced collapse

collapse specialised contracting decontamination

decontamination cleaning remediation environmental stewards

stewards risk mitigation and management waste disposal

How can we help you?

Whether it's a project you would like to discuss, an idea you would like to ponder, or perhaps you're just keen to learn more. We'd love to hear from you!

Get in touch

Search Liberty Industrial