Located in the Varanus Island hub, the Campbell Platform removal was contracted to McDermott in 2023. McDermott subsequently engaged Liberty Industrial for the complex task of deconstruction and waste recycling management of the platform upon transportation to the port via barge.
All structures were deconstructed using suitable demolition excavators, with demolition of taller structures achieved by high reach excavators, oxy cutting from EWP to pre-weaken structures before final induced collapse. The material from these structures were then downsized and moved to the processing area for segregating and processing using hot oxy-cutting and cold mechanical shearing, successfully achieving an impressive 99.5% recycling rate.
“We are extremely pleased with our ability to manage the complexities of the project by expanding our capabilities to include marine offloading operations and set a new benchmark for onshore decommissioning in Australia. We look forward to expanding on our already established and growing presence as a subject matter expert in onshore decommissioning in Australia and internationally.” said Warwyck Smith, Decommissioning Project Manager, Liberty Industrial.