SMOOTH SAILING | Our Liberty Industrial project team, led by Decommissioning Manager, Jed Van Iersel, masterfully executed the decommissioning, disassembly and disposal of the existing wharf and ship loader at Hay Point Terminal on behalf of BHP’s client McConnell Dowell.
We want to express our gratitude to our subcontractors, Tutt Bryant Group Limited (Heavy Lift Services including SPMT, Gantry, and Auxiliary Plant Hire), Cutrite (Specialist Concrete Cutting Services), and De-Consult Pty Ltd (Deconstruction Engineering Services), for their valuable contributions to the successful completion of the project.
Our media team, Smooth Motion Media Group produced a project video that documents the entire decommissioning journey from processing a small percentage of the wharf and ship loader at approximately 1,500t locally on-site with the remaining 5,000t shipped 3,070 nautical miles from Mackay, QLD to Henderson, WA via a Heavy Lift Vessel, making this project uniquely the first of its kind in the APAC region.
- Project Name: Hay Point Terminal – Disassembly & Disposal of Shiploader and Berth 2 Replacement Project
- Location: Mackay QLD & Henderson WA
- Client: McConnell Dowell
- Project Status: Completed 2023
- Stage 1
- Stage 1 Project Start Date: April 2021
- Stage 1 Project End Date: July 2021
- Stage 1 Duration: 4 months
- Stage 2
- Stage 2 Project Start Date: March 2022
- Stage 2 Project End Date: March 2023
- Stage 2 Duration: 12 months
Total Project Duration: 16 months